Project Description

SUBS Construction delivered precast concrete pit installation, conduit infrastructure and associated formwork, reinforcement and concrete packages for the Western Sydney International Airport development.

The works were completed within a congested service corridor involving multiple contractors and simultaneous infrastructure installations. Detailed coordination and staged delivery were used to maintain access and avoid conflicts with adjoining works.

Scope of Works

  • Installation of 24 precast concrete service pits

  • Excavation and preparation of pit foundations

  • Formwork, reinforcement and concrete works

  • Installation of electrical and services conduits

  • Connection of conduits to precast pits

  • Lifting and placement of precast structures

  • Backfilling and compaction around installed pits

  • Coordination with adjacent services and construction teams

  • Final surface reinstatement